Question # 105

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

A.

Refocus the sprint review meetings to demonstrate working software and seek feedback on the product.

B.

Reach out to other, more experienced teams to seek input as to how to present the technical details in a more informative manner.

C.

Explain the importance of the technical architecture and design presentations and improve the presentation format.

D.

Invite technical managers and architects who will be a more appropriate audience to their sprint reviews.

Full Access
Question # 106

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Full Access
Question # 107

One of the senior stakeholders on a project did not want to be engaged on a daily basis. During the iteration, the team encounters complexities but are convinced these issues can be resolved in time for the demo.

What should the agile practitioner do?

A.

Be transparent with all the stakeholders and make them aware of the issues encountered and the current project's status.

B.

Ensure the agile leader documents a risk in the risk register and communicates the risk to the project sponsor.

C.

Support the team's decision, and since the team is confident about being able to resolve the issues in time, do not raise the issues as risks with the stakeholders.

D.

Ask the product owner to make a decision as to whether or not all the stakeholders should be kept informed about the current project's status.

Full Access
Question # 108

How can an agile team working on a new product ensure alignment with external stakeholders?

A.

Ask the product owner to provide a detailed product specification document

B.

Conduct story-mapping exercises to clarify deliverables and release priorities

C.

Hold a kick-off meeting to assign roles and responsibilities.

D.

Work with the scrum master and stakeholders to ensure agile principles are followed

Full Access
Question # 109

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted, there is no value to the customers during this iteration.

What must the agile practitioner do?

A.

Add the new change request as a new user story in the product backlog for the upcoming iteration

B.

Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value C. Recommend cancelling the current iteration and plan the change request into the next iteration.

C.

Recommend that the product owner add this change request as a user story to the backlog for the current iteration

Full Access
Question # 110

During a six-week iteration, an issue is identified by a team member. After analysis, the team member determines that it will take at least two weeks to resolve. What should the team member do?

A.

Notify the product owner and begin resolution.

B.

Communicate the issue to the team in the next stand up meeting.

C.

Immediately begin resolution, and communicate it to the team during the retrospective.

D.

Work on the next activity, and communicate it to the team during the retrospective.

Full Access
Question # 111

An organization is shifting to an agile delivery methodology. An agile project manager has been assigned to the transformation project.

What should the agile project manager do to ensure a high level of adoption?

A.

Focus on not just the "what," but also the "how" of delivering projects.

B.

Ensure that there is buy-in from senior management to adopt agile.

C.

Identify strong product owners to ensure project teams are delivering value.

D.

Train the team on the fundamentals of the agile mindset and principles.

Full Access
Question # 112

A new agile project leader habitually becomes involved in the work from a support perspective and uses information radiators to ensure that all actions to remove impediments are visible to the team. What is the agile project leader doing?

A.

Practicing the servant leadership style of working with an agile team

B.

Building a collaborative teamwork culture

C.

Following a participatory decision-making model

D.

Adopting the practice of receiving feedback that will facilitate team improvement